Sabtu, 27 Februari 2016

Ive started painting the super structure

The interior of the super structure is painted and once again Ive discovered the hard way just how big a boat this is.

To begin, I am changing the paint schedule. After speaking with a commercial boat yard, they have me convinced to  only prime the interior of the super structure. The interior metal will get covered with closed cell spray foam then the liner will go over that. There is nothing such as UV or physical abuse that is going to break the primer down, so a top coat of paint is really not needed. I gave the interior a thorough blasting and applied three coats of epoxy primer.

Because I  have to weld the super structure to the hull, I taped off the the bottom edge of the metal so I will not have to grind away the primer later. Having the prime being burnt off by the welding is not only nasty, it can lead to the  primer gas mixing with the weld shielding gas and cause a defect in the weld. Porosity of the weld would be one example of a defect of this nature. Taping the joint is a heck of a lot faster and easier vs grinding.

Because paint over spray is not an issue with the interior, I decided to do this area first. Acting on the advice of some experienced paint people, I have taken a different approach to painting this part of the boat vs the hull. When I painted the hull, I blasted then primed, then started doing my fairing and filler work. The paint guys talked me into blasting the joints I want to do filler work, applying the filler, then blasting the rest of the metal then priming. Doing the work in this order will save me time as I will avoid some scuffing. This order of work will save me the most time on the roof. I  have a few areas I want to do some filler work on so I blasted those areas clean, and applied some filler. The filler work Im doing on the roof is more for function than for aesthetics. Ill sand those areas smooth, blast the rest of the roof, apply two coats of primer, and within the 72 hour chemical bond able time limit, Ill top coat the roof. No scuffing will be needed, and the more reliable chemical connection between primer and top coat is achieved.

The sides of the super structure is the area that everyone is going to see. For the sides, Im blasting all the joints and welds I want to fill over, then Im applying filler. Ill sand the filler smooth, blast the rest of the sides clean, and two coats of epoxy primer. While the primer is still hot, Ill apply two coats of sand able high build primer and long board that coat smooth. I know Ill be doing some more filler work on top of the high build, but thats  to be expected to get a nice finish. Once Im good with the high build surface ( my version of good is different than a professional body mans version). Ill spray another coat of primer to seal the high build, then top coat with my off white Acrylic Urethane. At this point the paint will be finished, and the list will be that much smaller.

Ill be posting updates as I work through the roof and sides.

The move to the launch site continues to get pushed back further. October seems doable, but early November seems more realistic. Once the paint work is finished, there is still work to be done here in the shop that will make the launch site assembly go faster. There is really no reason to slow things down by getting in a hurry. This is a big ass ed job, for one man to do by himself, and the time it takes is going to be the time it takes. I can only hope that the crap weather holds off until I have her dried in at the launch site, but Ive worked my whole life out in crap weather, so Im not to worried about me. I just dont want to compromises any work on the boat nor cost myself extra money.

Ill have the roof blasted and primed this weekend, and if all goes well, well have a off white roof to look at come Monday evening or Tuesday morning.

 






Cheers
Read More..

Senin, 15 Februari 2016

Ive started to finish

The last few weeks have found me rushing around to get the boat weather tight, and starting to organize my thoughts on  how best to manage the build to the finish. Like most things on this project, a lot of work needs to be done in a certain order before progress becomes visible.

With winter sneaking up on us, I had to get the barn put back together. The  mornings are getting colder and with the heavy dew making its way in to the barn, some of my tools are showing signs of rust. It took me a weekend to frame the opening back in, find the correct insulation, and trim the door opening to be ready for the crew who were re installing the door. I have to be able to fabricate much of the wood work for the interior in the barn, so having it weather tight and able to be heated is a big deal to keep the boat build moving. As I write this post, the barn is now back together, and while its still a mess, it sure feels good to have all the space back.

The dry exhaust stack for the engine room is one of those deals that not much else can be started  until this part is finished. Getting this finished turned out to be a bit of a pain as some poor measuring on my part  had me doing a few  things over. I framed access panels  on both the port and starboard side of the stack. The port side panel is larger as to allow me to install the exhaust pipe through the panel. I also had to configure the panel opening to work around the microwave cabinet so I dont have to remove the cabinet to replace the exhaust pipe.

The  exhaust stack was the last big welding job I  have to do inside the boat, and it feels good to be able to take the big generator out of the back of my truck and leave it in the shop.

Now that the foam is all finished, I wanted to get the ceiling in the master cabin, and get that room pretty much wrapped up. The ceiling is 3 1/4" pine bead board painted an off white. To make things easy on myself, I primed and painted one coat of top coat paint on the boards to prevent bare wood from showing once things start moving around. The ceiling  job was pretty straight forward, and the only tricky part was building the removable access panel on either side of the center beam. The access panel is for throttle and engine controls, hydraulic lines for the anchor winch, hydraulic lines for the steering system, and some conduit. The center beam is about 3/8" lower than the ceiling, and instead of wrapping it in bead board, I decided to wrap it in Cherry. I needed a board over 10 long, and instead of joining two together to get the length, I found a long one on the bottom of my now air dried stack of lumber. The longest boards I have also  happen to be the widest boards. As you can see from this picture, this particular board is over 19" wide and dried pretty darn straight. After I finish milling the faux beam, Ill install it in a day or so, and the master cabin will have a finished ceiling in it.After the master cabin ceiling is finished, another day of work should have the guest cabin dressing room ceiling completed which will also mean all the ceilings below will be finished.

Another small detail I needed to get squared away was building a proper set of steps to get in to the boat. Ive been using a ladder, and given the amount of trips and quantity of material I have to get on the boat, the ladder was the old accident waiting to happen. I  also have a lot of people who like to stop by, and any thing I can do to prevent them or me from getting hurt helps everyone in the long run. I also want to do right by the boat yard, and keep my operation in such a way as to minimize any exposure.

The tooling I need to finish the job is also getting to the point where Im comfortable. I wish I would have built all the engine room cabinets before we move her, as it would be nice to be able to start organizing the floating shop. Once in a while I do find myself borrowing a tool off of my truck, but for the most part the boat is now tooled up.

Boat building and schedules dont seem to get along in Conallville, but I"m going to take another stab at it. My plan is to have the bulk of the wood work finished by sometime in January. Once the wood work is finished and coated with urethane, I can focus on getting the needed systems up and running for our May/June launch. Without going into a bunch of detail, the systems Im talking about are AC/DC electric, hydraulic, and engine controls.

Cheers